Picture the bid tab on a $4.2 million Caltrans paving job with your firm at the top. Two weeks later the contract goes to the second bidder. Your DBE participation came in at 9.5 percent against a 12 percent goal, and the good faith effort file you submitted to explain the gap did not survive review. Contractors who lose a job this way have often worked hard on outreach. What they usually lack is a record that proves it.
This piece covers how to plan, run and document good faith outreach so a short-of-goal bid can withstand agency scrutiny. One caution before the details: good faith effort rules differ by funding source and by agency, and the federal DBE regulations were amended in 2024 and have continued to change. The special provisions and bid instructions for the specific contract always control. Read them first, and confirm current requirements with Caltrans or the awarding agency when anything is unclear.
What agencies are actually judging when you fall short of a DBE goal
On federally funded transportation work, the governing rules are in 49 CFR Part 26, the U.S. Department of Transportation's Disadvantaged Business Enterprise program. When a contract carries a DBE goal, a bidder has two options. It can meet the goal with committed, certified DBE subcontractors, suppliers or truckers, or it can show that it made adequate good faith efforts to meet the goal and still fell short.
The federal guidance tells agencies to weigh the quality, quantity and intensity of those efforts. The standard is whether you did what a bidder would reasonably be expected to do if it were actively and aggressively trying to reach the goal. A stack of form emails sent two days before bid opening does not meet that test. A file that shows early solicitations, real follow-up and documented reasons for every decision usually does.
Agencies can also look at what your competitors achieved. If the other bidders met the goal and you came in well below it, reviewers will want to know why your outreach produced less. Your file needs to answer that question before anyone asks it.
Where California contractors run into good faith requirements
On Caltrans state highway projects with federal funds, bidders use the department's DBE commitment form and its DBE good faith efforts information form. Local agency federal-aid projects are administered through Caltrans Local Assistance under the Local Assistance Procedures Manual. Chapter 9 of the manual covers the DBE program, and the commitment and good faith effort exhibits appear in the construction contract chapter. Exhibit numbers have been revised over time, so use the version referenced in your bid documents.
Transit agencies that receive Federal Transit Administration money, including LA Metro, BART, VTA and SFMTA, run their own DBE programs. Each sets its own submittal procedures. Some local programs have no federal funding behind them and still impose outreach requirements. The City of Los Angeles runs a subcontractor outreach program through its Bureau of Contract Administration. San Francisco's Local Business Enterprise program falls under Administrative Code Chapter 14B and is run by the Contract Monitoring Division. These local programs have their own forms and standards, and following the federal procedure will not satisfy them.
Working backward from bid opening
Most good faith effort disputes are lost on timing. Federal guidance requires bidders to give DBEs sufficient time to respond, and some agencies set specific minimum lead times for solicitations. Outreach that starts the week of bid opening is hard to defend no matter how well it is documented.
Submittal deadlines also vary. Caltrans has historically required good faith effort documentation within a short window after bid opening, often about four business days. The exact requirement is in the contract's special provisions, typically in the section on bidding, so read it for every job. On local federal-aid projects, each agency's bid documents set the deadline. Missing it can sink a bid outright.
A practical approach is to put an outreach calendar on your bid board the day you decide to pursue a job. The following schedule is a working target, not a regulation. Adjust it to the agency's stated lead times.
- Three weeks out: review the plans, confirm the DBE goal and identify the scopes you can break out.
- About two weeks out: pull DBE lists from the certification database, send written solicitations and place advertisements.
- One week out: call every DBE that has not responded, and log each call.
- The final days: collect and compare quotes, negotiate, and write down the reason for every decision.
- Bid day and after: submit the commitment information and the good faith effort package by the deadlines in the bid documents.
Building a file that holds up, one decision at a time
Start by breaking out the work. Agencies expect you to divide the job into economically feasible pieces DBEs can realistically perform, including work you would normally self-perform. On California highway and street jobs, likely candidates include traffic control and signage, striping and pavement markings, trucking, erosion control and stormwater work, survey and staking, landscaping and irrigation, concrete flatwork, curb and gutter, electrical and signals, and material supply such as aggregate, rebar and pipe. Record each scope with its estimated dollar value and the related bid item numbers. That list shows reviewers you looked for opportunities rather than waiting for DBEs to find you.
Next, identify certified firms through the California Unified Certification Program's DBE database. Search by NAICS code and work category, and focus on firms that work near the project. Save or print the results with the search date visible. That record shows which firms you found and when you found them.
Your solicitations should go out in writing and give DBEs what they need to bid: the scope, where to see plans and specifications, the quote deadline and a contact person. Follow up by phone with every firm that does not respond. Log the date, the person you reached and the outcome. Note any help you offered, such as access to plans or assistance with bonding, insurance or equipment. Agencies give weight to that kind of assistance.
Advertising is another common element, and many agencies look for it. Ads placed in trade and focused publications reach the subcontractors and suppliers most likely to bid. The Daily Reporter, for example, is certified by the Department of General Services as a trade and focused newspaper and runs these solicitations. Wherever your ad runs, keep proof of publication showing the run dates, because a reviewer will check that the ad appeared early enough to matter.
Before you submit, confirm the file contains:
- the scope breakout with values and bid items
- dated database search results
- copies of written solicitations and proof of delivery
- the follow-up call log
- proof of publication for advertisements
- every quote received, with a written reason for each one you did not use
Defending the quotes you didn't use and challenging a negative finding
Rejected quotes are where files most often fall apart. You are not required to accept a DBE quote that is unreasonably high. Federal guidance is also clear that some added cost alone is not a sufficient reason to reject a DBE, as long as the difference is reasonable. Agencies may compare the price difference with what other bidders paid for the same scope. Base your reasons for rejecting a quote on price, capability or the scope it covered. Note the dollar difference where price was the issue, and do not rely on general statements about qualifications.
If an agency finds your efforts inadequate on a federally assisted contract, the federal rules entitle you to administrative reconsideration. An official who did not take part in the original determination must decide it, and you can submit written documentation or argument. The file you assembled before bid opening is your case at that stage, because new outreach cannot be added after the fact. Keep in mind that the DBE commitments you list are binding after award. Replacing a listed DBE later requires agency approval under procedures set out in the contract.
Before your next federally funded or goal-bearing bid, open the special provisions and find the good faith effort section. Mark the submittal deadline and any required lead times on your bid board. Then count back three weeks from bid opening and start the scope breakout that day. A file that holds up under review depends on starting early.